ContactSite MapHome
 home < technical < recommended practices (RPs)

The AACE International Recommended Practices (RPs) are intended to be the main technical foundation of AACE International’s educational, and certification products and services. The RPs are a series of documents that contain valuable reference information that has been subject to a rigorous review process and recommended for use the AACE International Technical Board.  To purchase a hard-copy or CD-ROM of the RPs, please visit the Bookstore.

To date, AACE International's RPs includes the following documents:

(Rev. August 2007)
AACE International Recommended Practice No. 10S-90
TCM Framework:General Reference

(Rev. January 2006)
AACE International Recommended Practice No. 11R-88
TCM Framework:General Reference

(Rev. November 1990)
AACE International Recommended Practice No. 12R-89
TCM Framework:General Reference

(Rev. November 1990)
AACE International Recommended Practice No. 13S-90
TCM Framework:7.3 - Cost Estimating and Budgeting

(Rev. September 2006)
AACE International Recommended Practice No. 14R-90
TCM Framework:7.2 - Schedule Planning and Development

(Rev. November 1981)
AACE International Recommended Practice No. 15R-81
TCM Framework:3.3 - Investment Decision Making
6.1 - Asset Performance Assessment

(Rev. April 1991)
AACE International Recommended Practice No. 16R-90
TCM Framework:3.2 - Asset Planning
3.3 - Investment Decision Making

(Rev. August 1997)
AACE International Recommended Practice No. 17R-97
TCM Framework:7.3 - Cost Estimating and Budgeting

(Rev. February 2005)
AACE International Recommended Practice No. 18R-97
TCM Framework:7.3 - Cost Estimating and Budgeting

The Cost Estimate Classification System provides guidelines for applying the general principles of estimate classification to asset project cost estimates. Asset project cost estimates typically involve estimates for capital investment, and exclude operating and life-cycle evaluations. The Cost Estimate Classification System maps the phases and stages of asset cost estimating together with a generic maturity and quality matrix that can be applied across a wide variety of industries.

17R-97 provides a generic methodology for the classification of project cost estimates in any industry, while 18R-97 provides extensions and additional detail for applying the principles of estimate classification specifically to project estimates for engineering, procurement, and construction (EPC) work for the process industries.

An intent of the guidelines is to improve communication among all of the stakeholders involved with preparing, evaluating, and using project cost estimates.

(Rev. June 1998)
AACE International Recommended Practice No. 19R-97
TCM Framework:7.3 - Cost Estimating and Budgeting

This recommended practice presents benchmark information on the costs to prepare cost estimates (for engineering, procurement, and construction) in the process industries. It includes qualitative and quantitative lessons that cost engineers and estimators can use to benchmark their cost estimating experiences against. The data on preparation costs was used to develop a parametric cost model that can be used to estimate the cost of preparing estimates. The effort or cost to prepare a cost estimate is a secondary characteristic of a cost estimate classification. This Recommended Practice supports AACE International’s Recommended Practice 18R-97 Cost Estimate Classification System - as Applied in Engineering, Procurement, and Construction for the Process Industries.

(Rev. January 2003)
AACE International Recommended Practice No. 20R-98
TCM Framework:7.1 - Project Scope and Execution Strategy Development
7.2 - Schedule Planning and Development
7.3 - Cost Estimating and Budgeting

This guideline establishes the basic principles of codes of accounts (COA) for projects in any industry. It examines key characteristics including usage, content, structure and format and describes benefits of establishing standard COAs. Topics such as activity-based costing and work breakdown structures as they relate to COAs are addressed. The issues of properly defining a WBS and how it should be structured are outside the scope of this guideline. COAs are applicable to all phases of the asset life cycle, however, this guideline specifically addresses the project execution phases of asset design development through to start of normal operation.

A project code of accounts is a coded index of project cost, resource and activity categories. A complete COA includes definitions of the content of each account code and is methodically structured to facilitate finding, sorting, compiling, summarizing, defining and otherwise managing information the code is linked to. The information is used to support total cost management practices such as cost estimating, cost accounting, cost reporting, cost control, planning and scheduling. Other names used for COAs are coding matrices, coding structures, charge accounts, asset or material classification accounts, value categories, cost elements, work breakdown structures, resource breakdown structures and activity breakdown structures.

(Rev. January 2003)
AACE International Recommended Practice No. 21R-98
TCM Framework:7.1 - Project Scope and Execution Strategy Development
7.2 - Schedule Planning and Development
7.3 - Cost Estimating and Budgeting

This guideline is an industry-specific addendum to AACE International's generic guideline for project code of accounts (Recommended Practice No. 20R-98). This document describes recommended practices for codes of accounts (COA) as applied to engineering, procurement, and construction (EPC) projects in the process industries. "Process industries" are those with facilities whose main function is to perform a process. This includes chemical, petrochemical, hydrocarbon, pulp and paper, pharmaceutical, power generation, thermal, metallurgical, assembly, fabrication, and other processing. The primary characteristic of these industries, as it relates to codes of accounts, is that process or manufacturing equipment is the core or primary physical component of the facility. Equipment differentiates these projects from commercial construction and infrastructure where the core component is a structure, from software development projects where the core component is programming code, and so on.

COAs are applicable to all phases of the asset life cycle, but this guideline specifically addresses the EPC for creation, modification, or termination of a process facility. This guideline does not apply to code of accounts to support ongoing operations of process facilities. Properly defining a work breakdown structure (WBS), and other project structures, and deciding how they should be structured are outside the scope of this document.

A project code of accounts is a coded index of project cost, resource, and activity categories. A complete COA includes definitions of the content of each account code and is methodically structured to facilitate finding, sorting, compiling, summarizing, defining and otherwise managing the project information that is linked to the code. The information is used to support total cost management practices such as cost estimating, cost reporting, cost accounting, planning, and scheduling. Refer to 20R-98 for a more complete description of the principles of COAs.

(Rev. April 2004)
AACE International Recommended Practice No. 22R-01
TCM Framework:9.2 - Progress and Performance Measurement

This recommended practice of AACE International describes a direct method to measure, monitor and optimize construction and maintenance project labor productivity. The method described is statistical sampling of the work process, or: work sampling. The work process is made up of steps and activities that take input resources, add value, and produce the completed project. Understanding the capability of the process, or 'management system,' to produce efficiently is important for project planning and control. Sampling is a cost-effective way to provide information about the performance of the work process, i.e., about 'how' the work is done, and how to do it better. Work sampling complements conventional project management methodology, which typically tracks 'what' work is done.

Sampling provides project managers, supervisors, and the workforce with objective feedback re: the efficiency of the work process (not of individual workers, which is part of the foreman's job) - and the ability to respond quickly to adjust. In addition, it provides a measure of management's ability to effectively plan, coordinate, and control project execution. Analysis of the sampling data allows for prompt removal or reduction of roadblocks, optimizing the construction work process through redesign and innovation. Streamlining the work process ensures that performing productive work is made more convenient for the workforce, ensuring that, at all times, crafts and technicians have all the necessary tools, materials, parts, supplies, information, supervisory support and personal needs readily available. Work sampling, properly applied, recognizes that productivity results from an optimal work process, i.e., from 'managing smarter,' not from people working harder.

Construction labor productivity is a measure of work process efficiency. It can be defined as the ratio of the value labor produces to the value invested in labor. Productivity increases as needed labor resources are minimized and wasted efforts eliminated from the work process. This definition and the practice covered here treats productivity as a direct, absolute measure to be optimized.

(Rev. May 2007)
AACE International Recommended Practice No. 23R-02
TCM Framework:7.2 - Schedule Planning and Development

This recommended practice is for use by the project team members involved in the schedule planning process for any project type and in any industry. Many individuals contribute in the identification of activities, and having an experienced planner coordinate the process improves final quality and adds value to the planning process.

As a recommended practice of AACE International, identification of activities in schedule planning and development provides guidelines for the conversion of scope definition to specific activities and tasks required to complete a program or project. Identification of activities is a key planning step that takes place early in the schedule planning and development process which also includes estimating durations, determining and defining resources, and identifying external project constraints.

The scope definition of a program or project is generally described in various planning and technical documents, databases, or other deliverables. To begin the planning process, information in the scope documents must first be translated into manageable activities. For example, the scope may include the installation of a length of pipeline. Installing that pipeline may require designing, procuring, cutting, welding, erecting, and inspection activities. This process of expanding the high level scope or functional definition into the detailed work required for completion is the practice of "identification of activities".

(Rev. March 2004)
AACE International Recommended Practice No. 24R-03
TCM Framework:7.2 Schedule Planning and Development

As a recommended practice of AACE International, development of activity logic (also called network logic) in planning and scheduling provides guidelines for the sequencing of activities in a logical way generally before duration estimating can be performed. Logic is generally determined before durations are considered. Logic development methods include precedence diagramming, or arrow diagramming methods. Logic is the set of activities and dependency relationships between them. Logic dictates the planned sequencing of activities. A network diagram is often used to illustrate the logic.

Planning and scheduling are not the same. Planning is determining how the work will be done, while scheduling is the analysis and calculation of start and finish dates.

Logic enables the combination of activities to be arranged in one of the aforementioned formats so that a completion date can be established. Logic also enables backward passes to arrive at optimal overall schedule duration.
This recommended practice is for use by project team members involved in planning process, a continuation of activity identification process (reference TCM Framework section 8.2). As in identification of activities, many individuals contribute to the development of activity logic. Having an experienced planner coordinate the process improves final quality, and adds value to the planning process.

(Rev. April 2004)
AACE International Recommended Practice No. 25R-03
TCM Framework:6.4 Forensic Performance Assessment

This Recommended Practice focuses on identification of various methods for estimating lost labor productivity in construction claims. Often the claim is the result of one or more change order requests that cannot be fully resolved to capture their full and final effect on the entire project cost and schedule. Specifically, this Recommended Practice examines the issue in terms of claims for cost recovery of lost productivity. Therefore, the purpose of the Recommended Practice is to
  • Identify Lost Productivity Estimating Methodologies: That is, survey as many of the various methodologies employed in litigation throughout North America as can be identified;
  • Rank Order the Methodologies: That is, based on reliability, professional acceptance, case law and construction claims literature, rank the identified methodologies from most to least reliable with respect to documenting estimating damages in claim situations. While it may not be possible to state with certainty which methods are absolutely most or least reliable, it can be stated that under certain sets of circumstances some methods are generally considered more reliable than others. (CAUTION: This Recommended Practice was prepared on the basis of the author's understanding of Canadian and U.S. case law. It is recommended that anyone preparing a lost productivity claim seek appropriate legal advice on the methodology to be used. This is especially true if the claim is being pursued under national law other than Canada or the United States.)
  • Define and Discuss Each Methodology: That is, discuss the method and how it is employed. Also, when possible, discuss the strong and weak points of each method;
  • Identify Selected Studies Applicable to Each Methodology: Herein, identify as many studies and professional or technical papers as possible which will help the practitioner in learning more about and/or employing a particular method.

It needs to be noted that this Recommended Practice does not define in detail how one should properly perform the various analytical methods identified herein. The Recommended Practice gives a brief description of each method only in an effort to help claimants properly identify the method. That is, different claimants may have differing nomenclature for the same methodology. In this case, the brief description of each method is intended to help overcome this situation.


(Rev. October 2006)
AACE International Recommended Practice No. 28R-03
TCM Framework:7.3 - Cost Estimating and Budgeting
10.4 - Project Historical Database Management

This recommended practice provides a generic method of developing location factors in support of the Total Cost Management (TCM) cost estimating and budgeting and database management processes for construction related projects. The method applies to construction projects of all types including buildings, infrastructure, utilities, process plants, and so on. This generic method provides a basis for users to tailor their own detailed process around their own needs and computing capabilities. Location factors are used during preliminary project evaluations (i.e., Class 5 or 4 estimates). They are not intended to be used when preparing appropriation-quality estimates (i.e., Class 3 or better estimates).

(Rev. June 2007)
AACE International Recommended Practice No. 29R-03
TCM Framework:6.4 - Forensic Performance Assessment

(Rev. May 2007)
AACE International Recommended Practice No. 34R-05
TCM Framework:7.3 - Cost Estimating and Budgeting

AACE International’s Total Cost Management (TCM) Framework identifies a basis of estimate (BOE) document as a required component of a cost estimate. As a Recommended Practice (RP) of AACE International, the template outlined in the following sections provides guidelines for the structure and content of a cost basis of estimate.

In the TCM Framework, the BOE is characterized as the one deliverable that defines the scope of the project, and ultimately becomes the basis for change management. When prepared correctly, any person with capital project experience can use the BOE to understand and assess the estimate, independent of any other supporting documentation. A well-written BOE achieves those goals by clearly and concisely stating the purpose of the estimate being prepared (i.e. cost study, project options, funding, etc.), the project scope, pricing basis, allowances, assumptions, exclusions, cost risks and opportunities, and any deviations from standard practices. In addition the BOE is a documented record of pertinent communications that have occurred and agreements that have been made between the estimator and other project stakeholders.

(Rev. October 2006)
AACE International Recommended Practice No. 52R-06
TCM Framework:6.4 - Forensic Performance Assessment
7.2 - Schedule Planning and Development
10.2 - Forecasting
10.3 - Change Management

This Recommended Practice for Time Impact Analysis (TIA) is intended to provide a guideline, not to establish a standard. This recommended practice of AACE International on TIA provides guidelines for the project scheduler to assess and quantify the effects of an unplanned event or events on current project completion. While TIAs are usually performed by a project scheduler and can be applied on a variety of project types, the practice is generally used as part of the Total Cost Management (TCM) change management and forecasting processes on construction projects.

(Rev. September 2007)
AACE International Recommended Practice No. 53R-06
TCM Framework:9.2 - Progress and Performance Measurement
10.3 - Change Management

This Recommended Practice for Schedule Update Review is intended to provide a guideline, not to establish a standard. As a recommended practice of AACE International, this document provides guidelines for the project scheduler to create a professional schedule update or assess the reasonableness of changes to be made in a schedule due to a change of project status and progress. This recommended practice is associated with the Total Cost Management (TCM) progress and performance measurement, and change management processes on construction projects.

 
AACE International
Advertisements:
Membership |  Technical |  Education |  Certification |  Resources |  Listings |  Annual Meeting |  Contact |  Site Map |  Home