POSITION APPLIED FOR: PLANNING & COST CONTROL ENGINEER / PROJECT CONTROL ENGINEER
OBJECTIVES: Seeking for a company that provides job stability and career growth especially in the field of Project Management, Contract Administration, Quality Assurance and Control.
HIGHLIGHTS : Over 8 years experience in construction such as project planning and scheduling, site supervision, materials and cost estimates, drafting by using AutoCAD.
TRAINING AND EDUCATION:
College:Bachelor of Science in Civil Engineering
October 2000, New Era University
Tandang Sora, Quezon City Philippines
Trainings :
Formal
Planning & Scheduling Professional (PSP) Trained
Chicago Management Institute Abu Dhabi, UAE
Accredited by AACE International, USA
Cost Engineering (CCE) Trained
Chicago Management Institute Abu Dhabi, UAE
Accredited by AACE International, USA
Project Management Professional (PMP) Trained
a. Integration Management
b. Scope Management
c. Time Management
d. Cost Management
e. Quality Management
f. Procurement Management
g. HR Management
h. Communication Management
i. Risk Management
Chicago Management Institute Abu Dhabi, UAE
Accredited by PMI (Project Management Institute), USA
Overhead Under / Over Recovery Pursuant to Sub-Clause 52.3
Commercial and Contractual Tasks Procedure
Notices, Detailed Particulars and Calculation of Prolongation Costs
Preliminaries, Procurement, Variation Orders, Monthly Interim Payment Application/Certification
Contractors Entitlement to EOT and Prolongation
Costs & Dealing with Concurrent Delays
Depa Dec., Gen. Cont. & Maint. (LLC) - Sponsor
- Sheraton Dubai Creek
Project Management in Construction Course
-Cost Control, Supervising and Accounting
-Value Engineering
-Risk Management and Impact Analysis
-Project Cost Management
-PERT/CPM
-Cost Variance
-Project Monitoring and Control
-Commissioning and Project Closing/Termination
Knowledge Plus Academy
Quantity Surveying Course FIDIC
-FIDIC Conditions of Contract for Works of Civil Engineering General Conditions With Forms of Tender Agreement
-FIDIC Conditions of Contract for Works of Civil Engineering Conditions of Particular Application
-FIDIC Conditions of Contract for Plant and Design-Build for Electrical and Mechanical Plant
-FIDIC Conditions of Contract for Building and Engineering Works Designed by the Contractor
-FIDIC Short Form of Contract
-Business Economics
-Construction Technology
-Project Administration
-Construction Economics
-Design and Cost Appraisal
-International Calculation Procedure for Bill of Quantities/Variations
Knowledge Plus Academy
Primavera Project Planner for Project Management
Knowledge Plus Academy
MS Project 2003 for Project Management
MicroCADD Technologies
STAAD for Structural Analysis
MicroCADD Technologies
Autocad for Drafting and Design
Informatics Institute - SM Fairview Mall Branch
oIn-formal (Self-development / self-study / One-on-one Tutorials)
IntelliCAD for Drafting and Design
Sketch Up for 3D Drafting and Design
Vue 5 for Rendering and Animation
Adobe Photoshop / Elements for Graphic Design
Corel Draw for Graphic Design
3D Studio Max for Rendering and Animation
PC Troubleshooting and Networking
Visual Basic 6.0
XPAC (Microsoft Word, Excel, PowerPoint and Basic Internet)
Driving
SUMMARY OF EXPERIENCES & ACCOMPLISHMENTS:
March 20, 2007 Present
Depa Hotel Interiors - Abu Dhabi, Abu Dhabi, UAE
Position: Planning and QA/QC Engineer
Contact Person: Engr. Fadi Bikawi Planning Manager
Nature of work :
a. Contract administration and management
b. Calculates man-hours of the skilled workers on the site
c. Administer works based on contract.
d. Review documents issued by contractor such as Notices, RFI and implement it when necessary.
e. Preparing 2-week / 1 Month Look Ahead Plan(LAP)
f. Preparing monthly reports such as Cash Outflow and Inflow, Progress Status Reports, Manpower Status, Material Status Reports, Safety Status Reports etc.
g. Selecting the appropriate techniques and sequence of events for a particular project.
h. Presenting schedules of work, often with visual aids such as bar charts and procedures diagrams.
i. Using specialist planning computer software, such as Primavera, MS Project.
j. Monitoring progress throughout the construction process and comparing this with the projected schedule of work.
k. Liaising with the site agent and surveyor throughout the process, making adjustments to projects as necessary.
l. Review / approve contractors work programs submissions.
m. Advise and assist the contractor in the development of the work programs.
n. Record and report the actual progress of the work versus the planned work.
o. Ability to generate critical milestones for the construction stage for inclusion in tender documents through detailed discussions with the Design Manager, Design Team, evaluation of interfaces between buildings/ infrastructure etc.
p. Technical tender evaluations.
q. Consolidation and presentation of Consultants weekly reports.
r. Produce cash flows in P3 and be able to work with both office and site based Cost Managers.
s. Major coordination between primary infrastructure and building construction.
t. Evaluate designers and contractors detailed schedules and prepare the evaluation report. Conversant with the standard forms of contract.
u. Evaluate claims and make appropriate recommendations.
v. Understand and able to apply resources to schedule activities.
w. Handles project snagging, close-out and handing over.
x. Prepares forms such as request for information, material submittals, drawing submittals, etc.
y. Review approved materials, drawings.
z. Prepares Material Inspection Reports.
aa. Prepares Requests for Inspection and Approval (RFIA).
bb. Ensure that the materials used on site are based on the approved materials and
drawings.
cc. Prepares Snagging List and administer Project Close-out, and Handing Over.
dd. Preparing logs for materials, drawings, request for inspections, request for information and issues.
ee. Prepares Project Quality Plan and Quality Manual.
ff. Prepares Method Statement based on quality procedure.
JULY 2006 DECEMBER 2006
Euroasia Phil. Inc. Ortigas, Metro Manila
Contact Person: Mr. Joe Prea - 639178836939
Work Entry: Architectural CAD Designer
Project Information:
Under BOUYGUESSTROI BATIMENT INTERNATIONAL (Sakhalinsk Project)
Client: Exxon Neftegas Limited
Location: Yuzhno-Sakhalinsk , Russia
Nature of work :
a. Prepare drawings such as Architectural, Electrical, Mechanical, Structural, Electromechanical, Waterproofing Details, Fireproofing etc. using AutoCAD.
b. Prepare project materials estimates( BOM, BOQ )
c. Prepare as-built plans and Plotting
d. Project Monitoring and Site inspections for subcontractors billing
e. Scheduling and manpower allocation using Primavera Project Planner/MS Project
f. Updating/Reporting progress of the project in Primavera Project Planner/MS Project
g. Coordinates site works with the actual plan
h. Calculates man-hours of the skilled workers on the site
i. Evaluate subcontractors work based on workmanship and right specification
j. Prepares RFI, General Transmittals such as Material and Drawing submittals.
k. Prepares Project Quality Plan and Quality Manual.
l. Prepares Inspection Request such as Material Inspection Request, Installed Material Request based on functionality.
m. Prepares Snag List based on communication format made by the consultant /client.
n. Handles commissioning and testing of various work items.
2004 February 2006
CHIARA Construction , Cainta ,Rizal
Contact Person: Engr. Guinto - 639276493103
Nature of work :
a. Prepare drawings such as Architectural, Electrical , Mechanical , Structural , Electromechanical etc. using AutoCAD.
b. Prepares bidding documents for incoming projects.
c. Prepares project scheduling, manpower and safety of the projects and personnel involve
d. Project Monitoring and Site Inspection
e. Quality and Quantity Control of Sub-contractors Work
f. Prepare project estimates and work schedules
g. Handles all communication with other department involves in implementation of civil works and other works that may affect it.
h. Prepares inspection requests for material deliveries, installed materials on site.
i. Ensure that the shop drawings used are on the latest revision.
j. Prepares logs such as RFI, RFIA , materials, shop drawings, issues and concern.
k. Maintaining logs such RFI, RFIA, materials, shop drawings, issues and concern.
l. Prepares method statement for particular work items.
March 2004 January 2006
INFORMATICS COMPUTER INSTITUTE, Sta. Lucia East Grand Mall, Cainta Branch, Rizal
Contact Person: Ms. Lot Daza 6326817313
Nature of Work : Part-time Lecturer
Lecture basic and advance knowledge to the following subjects:
a. AutoCAD ( 2-Dimensional / 3-Dimensional)
b. MS Project 2002
c. Macromedia Dreamweaver MX 2004
d. Macromedia Flash MX 2004
e. Adobe Photoshop / Elements
f. Corel Draw
g. PC Troubleshooting and Networking
h. Visual Basic 6.0
i. XPAC (Microsoft Word, Excel, PowerPoint and Basic Internet)
February 2002 January 2004
DOUBLE STAR Construction Company, A. Bonifacio Quezon City
Contact Person: Engr. Crisostomo Villamar Jr. 09166688019
Nature of work :
a. Prepares working drawings such as Architectural, Electrical , Mechanical , Structural , Electromechanical etc. using AutoCAD.
b. Prepares bidding documents for incoming projects.
c. Prepares project scheduling, manpower and safety of the projects and personnel involve
d. Project Monitoring and Site Inspection
e. Quality and Quantity Control of Sub-contractors Work
f. Prepare project estimates and work schedules
g Handles all communication with other department involves in implementation of civil works and other works that may affect it.
h. Assisting on payroll
May 1998 January 2002
EJS ENGINEERING AND EQUIPMENT FABRICATOR, V